Kingsland
SecondarySPEN11 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2027
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Install second EHV circuit to Innerleithan Primary to offload Kingsland Primary and resolve single circuit risk. Remove Walkerburn Primary and transfer customer to Innerleithan network to increase security of supply and resolve asset risk and modernisation. | Thermal capacity | — | 2027 |
Capacity Forecast