Herrington Burn
PrimaryNPG66 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2027
First completion
2
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 0.6km of 66kV underground cable | Condition | +0.0 MVA | 2027 |
| Replacement of 66kV switchgear | Condition | +0.0 MVA | 2027 |
Voltage Levels (2)
66kV
1 busbarHerrington Burn 66 kVNPG
distribution Gen Headroom
N/A
Demand Headroom
N/A
Fault Level (3ph)
N/A
Firm Capacity
N/A
Data Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.