Hebburn
SecondaryNPG11 kV
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
1
Projects
Planned Reinforcement
DNO Network Development Reports+15 MVA
Total uplift
2026
First completion
4
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 1.3km of 66kV underground cables | Condition | +0.0 MVA | 2026 |
| Network rationalisation | Load | +15.4 MVA | 2027 |
| Replacement of 1.6km of 66kV overhead line | Condition | +0.0 MVA | 2033 |
| Replacement of 1.3km of 66kV underground cable | Condition | +0.0 MVA | 2033 |
Voltage Levels (3)
11kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3