Deeside Park
BSPSPEN132 kV 33 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2028
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Install new 132/33kV 60MVA grid transformer at Deeside Park and new 132kV bus-section circuit breaker at Connahs Quay to enable reconfiguration of Connahs Quay Grid Supply Point (GSP) to 2+2 supergrid transformer operational arrangement. Swap the Sixth-Avenue grid transformer with RAF Sealand circuit, and set bus-section reactor at Hawarden to normally open. Flexible Services will be procured to manage the network risk during the delivery of the proposed scheme. | Thermal capacity | — | 2028 |
Voltage Levels (2)
132kV
1 busbarData Source
Primary DNO:SP Energy Networks
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.