Clywedog Road
PrimarySPEN33 kV
Location
No coordinates available
Site Summary
Voltage Levels
1
Best Gen RAG
unknown
Best Gen Headroom
N/A
Best Demand Headroom
N/A
Operators
SPEN
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2027
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 33kV CBs | Modernisation | — | 2027 |
Voltage Levels (1)
Data Source
Primary DNO:SP Energy Networks
License:OGL v3