Burwell
BSPUKPNNGET132 kV 33 kV 11 kV
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
36
Projects
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2026
First completion
5
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| 1 x 33kV CB, 2 x grid transformers uprated | Load related reinforcement | — | 2026 |
| Additional 33kV Circuit | Load related reinforcement | — | 2026 |
| Establish new Grid substation | Load related reinforcement | — | 2027 |
| new circuits | Load related reinforcement | — | 2028 |
| Establish New Primary Substation | Load related reinforcement | — | 2028 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (4)
132kV
2 busbars33kV
1 busbarData Source
Distribution Operator:UK Power Networks
License:OGL v3
Transmission Owner:National Grid Electricity Transmission
License:NESO Open Data Licence (OGL v3.0 based)
Data sourced from publicly available DNO and TSO datasets. Indicative — verify directly with the operators before making connection decisions.