Admiral St
SecondarySPEN6.6 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2027
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Installation of assets across various 33/11kV Primary substations; 1 x 20MVA transformer, 2 x 32MVA transformers, 28 x 11kV circuit breakers and various secondary network upgrades. | Thermal capacity | — | 2027 |
Voltage Levels (1)
Data Source
Primary DNO:SP Energy Networks
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.