LABURNUM ROAD
PrimarySSEN11 kV
Network Hierarchy
CurrentLABURNUM ROAD
BSPALDERSHOT
GSPFLEET BRAMLEY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Fleet & Bramley GSP group to be split and a new 132kV switchboard installed at Bramley (Jul 2030)
- 3x33kV circuit ratings are 16.8MVA in summer. Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV reinforcement required at Fleet GSP
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.