ALTON LOCAL 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentALTON LOCAL 11 kV
BSPALTON & FERNHURST
GSPFLEET BRAMLEY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Alton & Fernhurst BSP group to be split (Sept 2025) Replace the AIS switchboad at Alton with a GIS switchboard (Jun 2028) A new 132kV switching station is to be established between Fleet GSP, Alton BSP and Fernhurst BSP to supply Alton and Fernhurst from Nursling under N-2 conditions (Aug 2028) Fleet & Bramley GSP group to be split and a new 132kV switchboard installed at Bramley (Jul 2030)
- Limited flexible headroom on the 132 kV circuits from Fleet. Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV fault level reinforcement required at Fleet GSP
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.